Cutomer prepares a technical and financial proposal in consultation with a PV service provider.
Please refer Sri Lanka Sustainable Energy Authority website for the updated list of registered service providers.
Customer applies for individual connection approval from CEB or LECO by submitting the technical proposal.
Specimen Request Letter
CEB/LECO grants approval based on network absorption capacity and in conformity to their technical guidelines.
Cutomer applies for a loan through the preferred Bank, submitting the loan application, the technical/financial proposal along with confirmation for connection by CEB/LECO.
Upon loan evaluation, bank clears the loan applications that would meet the project loan conditions, technical specifications, and other eligibility criteria.
The customer/bank pays the agreed portion of the project cost to the PV service provider.
The service provider install the system in accordance with specifications in the technical proposal in conformity to guidelines and specifications established by the project.
An accredited enginner registered with CEB / LECO inspects the installed rooftop solar PV system for compliance with project and utility guidelines and original technical proposal specification. The accredited engineer issues a compliance certificate.
Customer requests for system connection from CEB/LECO by submitting the compliance certificate.
CEB/LECO sign the connection agreement and provide the grid connection.
Customer submits the compliance certificate and the grid connection agreement to the bank for release of balance loan funds.
Bank checks the compliance and connection certificates and shall disburse the remaining loan funds to customer or directly to the service provider.
Cutomer prepares a technical and financial proposal in consultation with a PV service provider.
Please refer Sri Lanka Sustainable Energy Authority website for the updated list of registered service providers.
Customer applies for individual connection approval from CEB or LECO by submitting the technical proposal.
Specimen Request Letter
CEB/LECO grants approval based on network absorption capacity and in conformity to their technical guidelines.
Cutomer applies for a loan through the preferred Bank, submitting the loan application, the technical/financial proposal along with confirmation for connection by CEB/LECO.
Upon loan evaluation, bank clears the loan applications that would meet the project loan conditions, technical specifications, and other eligibility criteria.
The customer/bank pays the agreed portion of the project cost to the PV service provider.
The service provider install the system in accordance with specifications in the technical proposal in conformity to guidelines and specifications established by the project.
An accredited enginner registered with CEB / LECO inspects the installed rooftop solar PV system for compliance with project and utility guidelines and original technical proposal specification. The accredited engineer issues a compliance certificate.
Customer requests for system connection from CEB/LECO by submitting the compliance certificate.
CEB/LECO sign the connection agreement and provide the grid connection.
Customer submits the compliance certificate and the grid connection agreement to the bank for release of balance loan funds.
Bank checks the compliance and connection certificates and shall disburse the remaining loan funds to customer or directly to the service provider.